[Asian Development Bank] Commune Council Development Project 35274
Author Admin Date 2015.04.08 Views 798
Aid View
General Information Project/Program Project
Project Name Commune Council Development Project 35274
Duration Board Approval: 3-Dec.-2002 Closing Date Actual: 31-Dec.-2006
Donor Asian Development Bank (ADB)
Implementiong Organization Ministry of Interior, Department of Local Administration (DOLA)
Sector and/or Subsector Classification Infrastructure
Region 1,621 commune and sangkat councils
Financing Project Appraisal Total: USD 17.41million dollars Actual: USD 15.79million dollars ADB( Appraisal:USD 10million dollars, Actual: USD 9.98million), Netherlands Grant (Appraisal: USD 2.4 million dollars, Actual: USD 2.31 million), SIDA (Appraisal: USD 3million, Actual: USD 3.33million)
Analytical Information Stakeholders Asian Development Bank, Government of the Netherlands, Swedish International Development Cooperation Agency (SIDA), Ministry of Interior, Department of Local Administration, Ministry of Economy and Finance, Ministry of Land Management, Urban Planning, and Construction, National Committee for Support to Commune-Sangkat Councils, Office of Civil Registration of the Ministry of Interior, Provincial Local Administration Unit, Partnership for Local Governance, Project Technical Cell, United Nations Children's Fund,
Cross-cutting Issue Environment No relevant material is found.
Gender No relevant material is found.
Impact Analysis Project aligns with the 2002 election of commune council objectives (decentralization and deconcentration).
Effectiveness Ownership/Partnership Evaluation To increase ownership and partnership, the Project Technical Cell was created to give reports to the MOI and ADB. Although the PTC had trouble with ADB procedures during the initial stage of the project, quick learning and applying enabled them to carry out all project activities resulting high quality output.
Rating 4/5
Policy Coherence/Harmonization Evaluation Despite collaboration of donors, the ADB completion report does not explain any relevant material upon donor harmonization.
Rating 3/5
Evaluation Framework Evaluation The Ministry of Interior needs to increase its monitoring of the technical assistance. Most agencies, borrowers and the ADB is rated as positive and satisfactory. All project convenes were complied with except the deadline for the submission of the annual audit reports.
Rating 3/5
Alignment/Composition of Finance Evaluation Most components were according to schedule expect for initial delays of transferring the imprest account and the payment by provincial treasuries to the contractors for the construction of commune offices. According to the completion report, the alignment of finance was inadequate for implementing the project in a timely manner ( imprest account ceiling at 10percent), thus the disbursement turnover ration was about 3.5, the highest in the ADB Cambodia portfolio.
Rating 3/5
Other Remarks Commune Council Development Project 2 has been commencing from 2007. Contractors were having trouble dealing with more than one contract at a time; this may have decreased their project capacity and efficiency. This commune council project was the first big major project to support the decentralization of the government after the commune election.

 