go content



page info

DB on Aid Activities in Cambodia

> RESEARCH > DB on Aid Activities in Cambodia


News List
[Japan International Cooperation Agency (JICA)] The Project for Renovation of Technical School for Medical Care in the Kingdom of Cambodia
Author Admin Date 2015.04.10 Views 844
Aid View
General Information Project/Program Project
Project Name The Project for Renovation of Technical School for Medical Care in the Kingdom of Cambodia
Duration August 2004 - February 2006
Donor Japan International Cooperation Agency (JICA)
Implementiong Organization Technical School for Medical Care (TSMC)
Sector and/or Subsector Classification Health
Region Cambodia
Financing Approved loan amount: 774 million yen; Disbursed laon amount: 773 million yen
Analytical Information Stakeholders Technical School for Medical Care (TSMC), Pacific Consultants International, Obayashi Corporation, Japan International Cooperation Agency (JICA)
Cross-cutting Issue Environment No adverse effect with regard to the natural environment, land acquisition, resettlement of residents, or other matters has been reported.
Gender No infromation regarding gender
Impact Analysis Since both the First and Second Socio-Economic Development Plan (plan periods, 1996-2000 and 2001-2005) included elevation of the technical skills of health care and medical workers by the improvement of education and training, the projects has strong relevance in connection with the nation's development planning. The ex-post evaluation also says that the projects is highly consistent to the development needs of Cambodia. This is because there are high need for development of human resources (HR), notably for nursing, midwifery, lab technology, and X-ray technicians for work in the areas of basic health care, and this is relevant to the objectives of the project.
Effectiveness Ownership/Partnership Evaluation No infromation regarding ownership and partnership
Rating N.A.
Policy Coherence/Harmonization Evaluation No infromation regarding policy coherence and harmonization
Rating N.A.
Evaluation Framework Evaluation The evaluation was conducted from January 2010 to December 2010 by Miho Kawahatsu, Waseda Research Institue Corporation (WRI). The ex-post evaluation report specify the constraints of the evaluation, saying "it was not possible to obtain quantitiative information ont he TSMC's financial condiation because UHS controls the TSMC budget as the latter is an affiliate of the UHS."
Rating 3/5
Alignment/Composition of Finance Evaluation The project period was planned as starting August 2004 to January 2006, or 17 months; but required one more month more than that and the project was completed slightly later, in February 2006. Also, total project cost was 773 million yen; the amount at the appraisal was 774 million yen, so it was mostly accomplished as planned.
For sustainability issue, the ex-post evaluation report states that the sustainability of the project is fair, bacause some problems have been observed in terms of technical and financial aspects as well as current status of operation and maintanance.
Rating 3/5
Other Remarks Related Projects are "The project for Human Resource Development of Co-medicals (2003-2010)" and "The Project for Strengthening Human Resources Development System of Co-medicals (2010-2015)".

 

LIST



go top